[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126520":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126520,792,1,"单选题","采用支架法现浇预应力钢筋混凝土简支梁，支架卸落时应()进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","沿纵向从一端到另一端",false,{"key":16,"text":17,"correct":14},"B","沿横向从一边到另一边",{"key":19,"text":20,"correct":21},"C","沿纵向从跨中向两端",true,{"key":23,"text":24,"correct":14},"D","沿横向从中间向两边","【考点】支架法现浇预应力钢筋混凝土简支梁支架卸落要求。 梁模支架的卸落，应对称、均匀和有顺序地进行。卸落设备应放在适当的位置，当为排架式支架时应放在立柱处，当为梁式支架时应放在支架梁的支点处。支架卸落时，简支梁和连续梁应从跨中向两端进行，悬臂梁应先卸落挂梁及悬臂部分，然后卸落主跨部分。肋板梁等形式的上部构造，应按荷载传递的次序进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]