[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126510,792,1,"单选题","（2020年真题）工程造价控制在合理范围内的正确顺序，依次是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资估算→设计概算→施工图预算→竣工结算",true,{"key":16,"text":17,"correct":18},"B","投资估算→设计概算→施工决算→竣工结算",false,{"key":20,"text":21,"correct":18},"C","投资估算→施工图预算→设计概算→竣工结算",{"key":23,"text":24,"correct":18},"D","投资估算→施工图预算→施工决算→竣工结算","P210-212 把工程造价控制在合理的范围和核定的造价限额以内，就如通常规定的设计概算不得大于投资估算，施工图预算不得大于设计概算，竣工结算不得大于施工图预算。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]