[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126509,792,1,"单选题","（2019年）施工成本目标控制的依据是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程承包合同",true,{"key":16,"text":17,"correct":18},"B","项目目标管理责任书",false,{"key":20,"text":21,"correct":18},"C","企业管理制度",{"key":23,"text":24,"correct":18},"D","企业的项目管理规定","施工成本目标控制主要依据： (1)工程承包合同。 (2)施工成本计划。 (3)进度报告。 (4)工程变更。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]