[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126506,792,1,"单选题","（2018年真题）施工作业过程中，不需要及时修改或补充施工组织设计的情形是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程设计有重大变更",false,{"key":16,"text":17,"correct":14},"B","施工环境有重大变更",{"key":19,"text":20,"correct":14},"C","主要施工设备配置有重大调整",{"key":22,"text":23,"correct":24},"D","管理人员有变更",true,"本题考查的是施工组织设计编制注意事项。施工作业过程中发生下列情况之一时，施工组织设计应及时修改或补充：①工程设计重大变更；②施工资配重大调整；③施工环境重大改变。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]