[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126497":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126497,792,1,"单选题","依据有关规定，不属于危险性较大的分部分项工程的是（ ）。2017真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预应力筋穿束施工",true,{"key":16,"text":17,"correct":18},"B","水上打桩船作业",false,{"key":20,"text":21,"correct":18},"C","深10m的人工挖孔桩",{"key":23,"text":24,"correct":18},"D","起重机吊装梁板","考点:危险性较大的分部分项工程。预应力结构张拉施工属于危险性较大的分部分项工程，但预应力筋穿束施工不属于危险性较大的分部分项工程，属于干扰项。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]