[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126489,792,1,"单选题","混凝土结构中植入的钢筋，应进行（ ）试验。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","抗拔",true,{"key":16,"text":17,"correct":18},"B","抗弯",false,{"key":20,"text":21,"correct":18},"C","抗压",{"key":23,"text":24,"correct":18},"D","抗剪","考点:泵房施工质量检查与验收。二次混凝土或灌浆材料的强度符合设计要求；采用植筋方式时，其抗拔试验应符合设计要求。参见",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]