[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126474,792,1,"单选题","关于城镇供热直埋保温接头的说法，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一级管网现场安装的85%的接头应进行气密性检验",true,{"key":16,"text":17,"correct":18},"B","接头的保温和密封应在接头焊口检验合格后方可进行",false,{"key":20,"text":21,"correct":18},"C","预警线断路、短路检测应在接头安装完毕后进行",{"key":23,"text":24,"correct":18},"D","外观检查是质量验收的主控项目","《城镇供热管网工程施工及验收规范》CJJ282004第5.5.12条、第5.5.13条和第5.5.14条对直埋保温管接头的保温和密封规定如下：（8） 接头外护层安装完成后，必须全部进行气密性检验并应合格。故答案选A",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]