[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126463,792,1,"单选题","（2019年）下列属于绘制竣工图的依据的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工前场地绿化图",false,{"key":16,"text":17,"correct":14},"B","建(构)筑物所在场地原始地形图",{"key":19,"text":20,"correct":21},"C","设计变更文件",true,{"key":23,"text":24,"correct":14},"D","建筑物沉降、位移等变形观测资料","绘制竣工图的依据： (1)设计总平面图、单位工程平面图、纵横断面图和设计变更资料； (2)控制测量资料、施工检查测量及竣工测量资料。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]