[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126421":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1126421,792,1,"单选题","施工过程中各个阶段工程测量的各项内业计算准备工作应结合()进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标文件",false,{"key":16,"text":17,"correct":18},"B","设计文件",true,{"key":20,"text":21,"correct":14},"C","专项安全施工方案",{"key":23,"text":24,"correct":14},"D","技术交底","(1 ) 开工前应结合设计文件、施工组织设计，提前做好工程施工过程中各个阶段的工程测量的各项内业计算准备工作，并依照内业准备进行施工测量。故答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]