[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126396,792,1,"单选题","某供热管网的设计压力为1.6MPa，其严密性试验压力应为（ ）MPa。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1.4",false,{"key":16,"text":17,"correct":14},"B","1.6",{"key":19,"text":20,"correct":14},"C","1.8",{"key":22,"text":23,"correct":24},"D","2.0",true,"考点:供热管网支吊架安装。供热管网的严密性试验的试验压力为1.25倍的设计压力，且不得低于0.6 MPa，本题设计压力为1.6 MPa×1.25=2.0 MPa，选项D正确。参见",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]