[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126387,792,1,"单选题","热力管网试运行应连续运行()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","24h",false,{"key":16,"text":17,"correct":14},"B","36h",{"key":19,"text":20,"correct":14},"C","48h",{"key":22,"text":23,"correct":24},"D","72h",true,"5) 试运行期间发现的问题，属于不影响试运行安全的，可待试运行结束后处理；若 影响试运行安全，必须当即停止试运行，进行处理。试运行的时间，应从正常试运行状态 的时间开始计算连续运行72h。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]