[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126377,792,1,"单选题","关于无压管道闭水试验准备工作的说法，错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管道及检查井外观质量已验收合格",false,{"key":16,"text":17,"correct":14},"B","管道未回填土且沟槽内无积水",{"key":19,"text":20,"correct":21},"C","试验管段所有敞口应封闭",true,{"key":23,"text":24,"correct":14},"D","做好水源引接、排水疏导等方案","无压管道闭水试验准备工作有：(1)管道及检查井外观质量已验收合格；(2)管道未回填土且沟槽内无积水；(3)全部预留孔应封堵，不得渗水；(4)管道两端堵板承载力经核算应大于水压力的合力；除预留进出水管外，应封堵坚固，不得渗水；(5)顶管施工，其注浆孔封堵且管口按设计要求处理完毕，地下水位于管底以下；(6)应做好水源引接、排水疏导等方案。故答案选C",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]