[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1126355,792,1,"单选题","（2020年真题）竖井马头门破除施工工序有：①预埋暗梁、②破除拱部、③破除侧墙、④拱部地层加固、⑤破除底板，正确的顺序为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④→⑤",false,{"key":16,"text":17,"correct":18},"B","①→④→②→③→⑤",true,{"key":20,"text":21,"correct":14},"C","①→④→③→②→⑤",{"key":23,"text":24,"correct":14},"D","①→②→④→③→⑤","P116-118 竖井初期支护施工至马头门处应预埋暗梁及暗桩，并应沿马头门拱部外轮廓线打入超前小导管，注浆加固地层。破除马头门前，应做好马头门区域的竖井或隧道的支撑体系的受力转换。马头门开挖施工应严格按照设计要求，并应采取加强措施。马头门的开挖应分段破除竖井井壁，宜按照先拱部、再侧墙、最后底板的顺序破除。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]