[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126349,792,1,"单选题","将结构断面分成两个部分，即分成上下两个工作面，分步开挖的浅埋暗挖施工方法称为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","台阶法",true,{"key":16,"text":17,"correct":18},"B","全断面法",false,{"key":20,"text":21,"correct":18},"C","中洞法",{"key":23,"text":24,"correct":18},"D","单侧壁导坑法","台阶法施工就是将结构断面分成两个或几个部分，即分成上下两个工作面或几个工作面，分步开挖。单侧壁导坑法是将断面分成三块：侧壁导坑、上台阶、下台阶。地下工程断面采用一次开挖成型的施工方法叫全断面开挖法。中洞法施工就是先开挖中间部分（中洞），在中洞内施作梁、柱结构，然后再开挖两侧部分（侧洞），并逐渐将侧洞顶部荷载通过中洞初期支护转移到梁、柱结构上。根据题干的描述，很显然是指A选项。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]