[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126342":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126342,792,1,"单选题","（2020年真题）在软弱地层的基坑工程中，支撑结构挡土的应力传递路径是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","土压力→围檩→围护桩→支撑",false,{"key":16,"text":17,"correct":14},"B","土压力→围护桩→支撑→围檁",{"key":19,"text":20,"correct":14},"C","土压力→围檩→支撑→围护桩",{"key":22,"text":23,"correct":24},"D","土压力→围护桩→围檩→支撑",true,"P93-99 在软弱地层的基坑工程中，支撑结构承受围护墙所传递的土压力、水压力。支撑结构挡土的应力传递路径是围护(桩)墙→围檩(冠梁)→支撑。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]