[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126337":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126337,792,1,"单选题","（2018年真题）下列基坑放坡要求中，说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","放坡应以控制分级坡高和坡度为主",false,{"key":16,"text":17,"correct":14},"B","放坡设计与施工时应考虑雨水的不利影响",{"key":19,"text":20,"correct":21},"C","上级放坡坡度宜缓于下坡放坡坡度",true,{"key":23,"text":24,"correct":14},"D","分级放坡时，宜设置分级过度平台","本题考查的是基坑放坡要求。下级放坡坡度宜缓于上坡放坡坡度。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]