[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126333,792,1,"单选题","采用明沟排水，当沟槽开挖接近地下水位时，施工顺序为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","挖集水井→安装水泵排水→挖临时排水沟→挖排水沟外侧的土→加深排水沟",true,{"key":16,"text":17,"correct":18},"B","挖临时排水沟→挖排水沟外侧的土→加深排水沟→安装水泵排水→挖集水井",false,{"key":20,"text":21,"correct":18},"C","挖临时排水沟→安装水泵排水→挖集水井→挖排水沟外侧的土→加深排水沟",{"key":23,"text":24,"correct":18},"D","挖集水井→挖临时排水沟→挖排水沟外侧的土→安装水泵排水→加深排水沟","坑（槽）开挖采用明沟排水时，应分层下挖，即先进行基坑（槽）的开挖，当开挖到接近地下水位时，在基坑（槽）的适当位置挖设集水井并安装水泵，然后在基坑四周（沟槽一般在中间）开挖临时排水沟，使地下水经排水沟汇集到集水井并由水泵排出，继续开挖排水沟两侧的土，当挖掘面接近排水沟底时，再加深排水沟，直到基坑（槽）底到达设计标高为止。排水沟底要始终保持比土基面低不小于0.3m。当坑（槽）面积较大时，可挖设纵横交错的多条临时排水沟。排水沟应以3％～5％的坡度坡向集水井，使地下水不断地流入排水沟，再汇集到集水井，由水泵排除。挖土顺序应从集水井、排水沟处逐渐向远处挖掘，使基坑（槽）开挖面始终不被水浸泡。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]