[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126318":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126318,792,1,"单选题","（2019年）关于预应力混凝土结构模板拆除的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","侧模应在预应力张拉前拆除",true,{"key":16,"text":17,"correct":18},"B","侧模应在预应力张拉后拆除",false,{"key":20,"text":21,"correct":18},"C","模板拆除应遵循先支先拆，后支后拆的原则",{"key":23,"text":24,"correct":18},"D","连续梁结构的模板应从支座向跨中方向依次循环卸落","预应力混凝土结构的侧模应在预应力张拉前拆除；底模应在结构建立预应力后拆除。 模板、支架和拱架拆除应遵循先支后拆、后支先拆的原则。 简支梁、连续梁结构的模板应从跨中向支座方向依次循环卸落；悬臂梁结构的模板宜从悬臂端开始顺序卸落。故选项A正确。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]