[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126308,792,1,"单选题","关于预应力钢铰线张拉的说法，错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","构件混凝土强度不得低于设计值的75%",false,{"key":16,"text":17,"correct":14},"B","当设计无要求时，张拉顺序可采用对称张拉",{"key":19,"text":20,"correct":14},"C","长20m梁直线预应力钢铰线可采用一端张拉方式",{"key":22,"text":23,"correct":24},"D","工作人员可站在张拉千斤顶后面随时观察张拉情况",true,"预应力筋张拉应符合下列要求： (1) 混凝土强度应符合设计要求，设计未要求时，不得低于强度设计值的75%。 (2) 预应力筋张拉端的设置应符合设计要求。当设计未要求时，应符合下列规定：曲线预应力筋或长度大于等于25m 的直线预应力筋，宜在两端张拉；长度小于25m的直线预应力筋，可在一端张拉。(4) 预应力筋的张拉顺序应符合设计要求；当设计无要求时，可采取分批、分阶段对称张拉。排除法选D,该选项原文教材中没提及",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]