[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126298,792,1,"单选题","关于箱涵顶进施工的做法，错误的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由上向下开挖",false,{"key":16,"text":17,"correct":14},"B","不超前挖土",{"key":19,"text":20,"correct":21},"C","逆坡挖土",true,{"key":23,"text":24,"correct":14},"D","严禁扰动基底土壤","应在列车运行间隙时间内进行。在开挖面应设专人监护，应按照测刃脚坡度及规定的进尺由上往下开挖，侧刃脚进土应在0.1m以上。开挖面的坡度不得大于1：0.75，并严禁逆坡挖土，不得超前挖土。严禁扰动基底土壤。挖土的进尺可根据土质确定，宜为0.5m；当土质较差时，可按千斤顶的有效行程掘进，并随挖随顶防止路基塌方。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]