[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126297":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126297,792,1,"单选题","采用悬臂浇筑法施工多跨预应力混凝土连续梁时，正确的浇筑顺序是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0号块→主梁节段→边跨合龙段→中跨合龙段",true,{"key":16,"text":17,"correct":18},"B","0号块→主梁节段→中跨合龙段→边跨合龙段",false,{"key":20,"text":21,"correct":18},"C","主梁节段→0号块→边跨合龙段→中跨合龙段",{"key":23,"text":24,"correct":18},"D","主梁节段→0号块→中跨合龙段→边跨合龙段","考察悬臂浇筑法的浇筑顺序，施工顺序为0号块→分段浇筑主梁至贺龙前段→浇筑边跨主梁合龙段→最后浇筑中跨合龙段形成连续梁体系。所以本题的正确答案为A@##",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]