[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126293":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126293,792,1,"单选题","采用悬臂浇筑法施工预应力钢筋混凝土连续梁时，正确的合龙顺序是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","次跨一中跨一边跨",false,{"key":16,"text":17,"correct":14},"B","中跨一边跨一次跨",{"key":19,"text":20,"correct":21},"C","边跨一次跨一中跨",true,{"key":23,"text":24,"correct":14},"D","次跨一边跨一中跨","(2)预应力混凝土连续梁合龙顺序一般是先边跨、后次跨、再中跨。所以，选C",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]