[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126289":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1126289,792,1,"单选题","相邻的无支护基坑深浅不等时，一般采用()的开挖施工顺序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先浅后深",false,{"key":16,"text":17,"correct":18},"B","先深后浅",true,{"key":20,"text":21,"correct":14},"C","同时进行",{"key":23,"text":24,"correct":14},"D","交替进行","(3) 沉桩顺序：对于密集桩群，自中间向两个方向或四周对称施打；根据基础的设计高程，宜先深后浅；根据粧的规格，宜先大后小，先长后短。同理推出选B",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]