[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126288,792,1,"单选题","关于打入桩施工技术要求的说法，错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","水泥混凝土桩要达到100%设计强度并具有28d龄期",false,{"key":16,"text":17,"correct":14},"B","在桩的打入过程中，应始终保持锤、桩帽和桩身在同一轴线上",{"key":19,"text":20,"correct":21},"C","打密集群桩，一般是由前排向后排打",true,{"key":23,"text":24,"correct":14},"D","打桩时以控制桩尖设计标高为主","(3) 沉桩顺序：对于密集桩群，自中间向两个方向或四周对称施打；根据基础的设计高程，宜先深后浅；根据粧的规格，宜先大后小，先长后短。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]