[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126266":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126266,792,1,"单选题","（2016年真题）某市政工程网络计划如下图，其关键线路是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①→②→③→⑤→⑦→⑧",false,{"key":16,"text":17,"correct":14},"B","①→②→③→④→⑥→⑦→⑧",{"key":19,"text":20,"correct":21},"C","①→②→③→⑤→⑥→⑦→⑧",true,{"key":23,"text":24,"correct":14},"D","①→②→④→⑥→⑦→⑧","本题考查的是工程进度计划方法。总工期为3+6+12+9+4=34。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]