[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126264":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126264,792,1,"单选题","（2017年真题）下列因素中，不属于施工进度计划编制依据的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程项目所在地自然条件",false,{"key":16,"text":17,"correct":14},"B","施工单位投入资源情况",{"key":19,"text":20,"correct":14},"C","工程项目所在地资源情况",{"key":22,"text":23,"correct":24},"D","建设单位组织机构设置",true,"考查施工进度计划编制依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]