[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126238":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126238,792,1,"单选题","（2014年真题）关于石灰粉煤灰稳定碎石混合料基层碾压。错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可用薄层贴补方法找平",true,{"key":16,"text":17,"correct":18},"B","采用先轻型后重型压路机碾压",false,{"key":20,"text":21,"correct":18},"C","混合料每层最大压实厚度为200mm",{"key":23,"text":24,"correct":18},"D","混合料可用沥青乳液进行养护","石灰粉煤灰稳定碎石混合料基层压实与养护施工要点：（1)混合料施工时由摊铺时根据试验确定的松铺系数控制虚铺厚度，混合料每层最大压实厚度为200mm，且不宜小于l00mm。（2）碾压时采用先轻型、后重型压路机碾压。（3）禁止用薄层贴补的方法进行找平。（4）混合料的养护采用湿养，始终保持表面潮湿，也可采用沥青乳液和沥青下封层进行养护，养护期为7～14d。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]