[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126232,792,1,"单选题","（2012年真题）热拌沥青混合料面层摊铺碾压，说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拌和物的摊铺，运料车不少于4辆以满足连续施工",false,{"key":16,"text":17,"correct":14},"B","沥青混合料路面碾压完成后就可以开放交通",{"key":19,"text":20,"correct":21},"C","压实应按初压、复压、终压包括成型三个阶段进行",true,{"key":23,"text":24,"correct":14},"D","碾压应从中心线向两端进行","本题考查的是沥青混凝土路面施工工艺要求。应复查基层和附属构筑物质量，确认符合规范要求；宜采用两台（含）以上摊铺机成梯队作业，进行联合摊铺，前后摊铺机宜相距10~30m；上面层的纵缝宜安排在车道线上；摊铺后紧跟碾压工序，压实分初压、复压、终压（包括成型）三个阶段。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]