[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126204":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126204,792,1,"单选题","（2017年真题）关于燃气管道现场焊接固定口防腐的说法，错误的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","现场无损探伤和分段试压合格后方可进行补口防腐",false,{"key":16,"text":17,"correct":14},"B","防腐前钢管表面的处理等级应不低于PSa2级",{"key":19,"text":20,"correct":21},"C","焊接防腐涂层固化后立即进行电火花仪检测",true,{"key":23,"text":24,"correct":14},"D","用电火花仪检查出现击穿气孔时，应做加强防腐","弯头及焊缝防腐可采用冷涂方式，其厚度、防腐层数与直管段相同，防腐层表层固化2h后进行电火花仪检测。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]