[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126191,792,1,"单选题","（2014年真题）供热管道保温材料进场后应进行（ ）测定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","密度",false,{"key":16,"text":17,"correct":14},"B","含水率",{"key":19,"text":20,"correct":21},"C","导热系数",true,{"key":23,"text":24,"correct":14},"D","渣球含量","材料进场时应对品种、规格、外观等进行检查验收，并从进场的每批保温材料中任选1-2组试样进行导热系数测定，导热系数超过设计取定值5%以上的材料不得使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]