[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126163":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":24},1126163,792,1,"单选题","（2011年真题）右图为隧道正台阶环形开挖法的示意图，施工中应最先开挖（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","a",false,{"key":16,"text":16,"correct":17},"B",true,{"key":19,"text":20,"correct":14},"C","c和d",{"key":22,"text":23,"correct":14},"D","e","本题考查的知识点是正台阶环形开挖法的施工作业顺序。正台阶环形开挖法一般将断面分成环形拱部（图中的B、C、d）、土部核心土(a)、下部台阶(e)三部分。根据断面的大小，环形拱部又可分成几块交替开挖。正台阶环形开挖法的施工作业顺序为：用人工或单臂掘进机开挖环形拱部一架立钢支撑一喷混凝土。@##",{"id":6,"name":26,"category":27,"favorite":28},"二建市政工程实务","建筑工程",0]