[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126159,792,1,"单选题","（2014年真题）暗挖隧道环形开挖预留核心土法施工工艺流程中，紧接在“开挖环形拱部→架立钢支撑→喷射混凝土→”后的工序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","封底",false,{"key":16,"text":17,"correct":14},"B","二次衬砌",{"key":19,"text":20,"correct":14},"C","接长钢支撑",{"key":22,"text":23,"correct":24},"D","开挖核心土和下台阶",true,"环形开挖预留核心土法施工作业流程：用人工或单臂掘进机开挖环形拱部→架立钢支撑→喷混凝土。在拱部初次支护保护下，为加快进度，宜采用挖掘机或单臂掘进机开挖核心土和下台阶，随时接长钢支撑和喷混凝土、封底。视初次支护的变形情况或施工步序，安排施工二次衬砌作业。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]