[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126153,792,1,"单选题","（2015年真题）采用锁口管接头的地下连续墙的施工工序包括：①开挖沟槽②吊放钢筋笼③下导管④吊放接头管⑤拔出接头管⑥灌注水下混凝土⑦导墙施工。正确的地下连续墙施工顺序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","⑤→⑦→①→④→②→③→⑥",false,{"key":16,"text":17,"correct":14},"B","①→⑦→④→②→③→⑤→⑥",{"key":19,"text":20,"correct":14},"C","⑦→④→①→③→②→⑥→⑤",{"key":22,"text":23,"correct":24},"D","⑦→①→④→②→③→⑥→⑤",true,"本题考查的是深基坑支护结构与变形控制。本题通过排除法即可得到答案。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]