[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126131":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126131,792,1,"单选题","（2012年真题）在设计未规定的情况下，采用后张法施工的C50预应力混凝土T型梁强度达到（ ）MPa时可进行预应力张拉。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","25",false,{"key":16,"text":17,"correct":14},"B","30",{"key":19,"text":20,"correct":14},"C","35",{"key":22,"text":23,"correct":24},"D","37.5",true,"本题考查的是城市桥梁工程先张法和后张法施工质量的过程控制。对于后张法施工，进行预应力张拉时，构件的混凝土强度应符合设计要求，设计为规定时，不应低于设计强度等级值的75%。本题中为C50预应力混凝土，50×75%=37.5Mpa，只有D选项符合要求。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]