[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126130,792,1,"单选题","（2012年真题）关于桥梁工程卸落支架顺序说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","满布拱架可从拱顶向拱脚依次循环卸落",false,{"key":16,"text":17,"correct":14},"B","连续梁宜从跨中向支座依次循环卸落",{"key":19,"text":20,"correct":21},"C","简支梁宜从支座向跨中依次循环卸落",true,{"key":23,"text":24,"correct":14},"D","悬臂梁应先卸挂梁及悬臂支架，后卸去挂梁主跨内支架","本题考查的是城市桥梁工程先张法和后张法施工质量的过程控制。卸落支架和拱架应按拟定的卸落程序进行，分几个循环卸完，卸落量开始宜小，以后逐渐增大，每一循环中在纵向应对称均衡卸落，在横向应同时一起卸落。简支梁、连续梁宜从跨中间支座依次循环卸落。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]