[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126119,792,1,"单选题","（2013年真题）关于先张法和后张法预应力梁施工的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","两者使用的预制台座不同",false,{"key":16,"text":17,"correct":14},"B","预应力张拉都需采用千斤顶",{"key":19,"text":20,"correct":21},"C","两者放张顺序一致",true,{"key":23,"text":24,"correct":14},"D","后张法预应力管道需压浆处理","本题考查的是城市桥梁工程先张法和后张法施工质量的过程控制。先张法施工工艺是在预埋构架时，先在台座上涨拉钢筋，然后支模浇筑混凝土使构件成型的施工方法。后张法是在混凝土构件达到一定的强度后，在构件预留孔道中穿入预应力筋，用机械张拉，是预应力筋对混凝土构件施加压力。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]