[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126116,792,1,"单选题","（2013年真题）关于箱涵顶进施工的做法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由上向下开挖",false,{"key":16,"text":17,"correct":14},"B","不超前挖土",{"key":19,"text":20,"correct":21},"C","逆坡挖土",true,{"key":23,"text":24,"correct":14},"D","严禁扰动基底土壤","本题考查的是管涵施工技术要求。应在列车运行间隙时间内进行。在开挖面应设专人监护。应按照侧刃脚坡度及规定的进尺由上往下开挖，侧刃脚进土应在0.1m以上。开挖面的坡度不得大于1:0.75，并严禁逆坡挖土，不得超前挖土。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]