[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126114,792,1,"单选题","（2015年真题）采用悬臂浇筑法施工多跨预应力混凝土连续梁时，正确的浇筑顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0号块→主梁节段→边跨合龙段→中跨合龙段",true,{"key":16,"text":17,"correct":18},"B","0号块→主梁节段→中跨合龙段→边跨合龙段",false,{"key":20,"text":21,"correct":18},"C","主梁节段→0号块→边跨合龙段→中跨合龙段",{"key":23,"text":24,"correct":18},"D","主梁节段→0号块→中跨合龙段→边跨合龙段","本题考查的的现浇预应力（钢筋）混凝土连续梁施工技术。应当是先浇筑0号块，然后是墩顶梁端两则对称悬浇梁段，接着是边孔支架现浇梁段，最后是主梁跨中合龙段。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]