[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126113,792,1,"单选题","（2011年真题）设置现浇预应力混凝土连续梁支架预拱度时，不考虑的变形值是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","卸架后上部构造本身及活载一半所产生的竖向挠度",false,{"key":16,"text":17,"correct":14},"B","支架在荷载作用下的弹性压缩和非弹性压缩",{"key":19,"text":20,"correct":21},"C","支架基底在荷载作用下的弹性沉降",true,{"key":23,"text":24,"correct":14},"D","由混凝土收缩及温度变化而引起的挠度","本题考查的知识点是现浇预应力钢筋混凝土连续梁施工技术要求。现浇预应力钢筋混凝土连续梁支架的弹性、非弹性变形及基础的允许下沉量应满足施工后梁体设计标高的要求。因此，需在施工时设置一定数值的预拱度，其值为以下各项变形值之和：①卸架后上部构造本身及活载一半所产生的竖向挠度；②支架在荷载作用下的弹性压缩；③支架在荷载作用下的非弹性压缩；④支架基底在荷载作用下的非弹性沉陷；⑤由混凝土收缩及温度变化而引起的挠度。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]