[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126110":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126110,792,1,"单选题","（2013年真题）关于静力压桩法施工混凝土预制桩的说法，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","桩顶不易破坏",false,{"key":16,"text":17,"correct":14},"B","施工时无冲击力",{"key":19,"text":20,"correct":14},"C","沉桩精度较高",{"key":22,"text":23,"correct":24},"D","沉桩过程不产生挤土效应",true,"本题考查的是沉入桩施工技术要求。静力压桩正是通过挤压土体才将桩压入土体的，所以选项D错误。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]