[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126107":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126107,792,1,"单选题","后张法预应力筋张拉后，孔道（ ）压浆。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","宜尽早",false,{"key":16,"text":17,"correct":14},"B","不急于",{"key":19,"text":20,"correct":21},"C","应及时",true,{"key":23,"text":24,"correct":14},"D","暂缓","P273-275 压浆与封锚： (1)张拉后应及时进行孔道压浆，宜采用真空辅助法压浆;水泥浆的强度应符合设计要求，且不得低于30MPa。 (2)压浆时排气孔、排水孔应有水泥浓浆溢出。应从检查孔抽查压浆的密实情况，如有不实应及时处理。 (3) 压浆过程中及压浆后48h 内，结构混凝土的温度不得低于5℃。当白天气温高于35℃时，压浆宜在夜间进行。 (4)压浆后应及时浇筑封锚混凝土。封锚混凝土的强度应符合设计要求，不宜低于结构棍凝土强度等级的80% ，且不得低于30MPa 。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]