[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126093":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126093,792,1,"单选题","月、旬(或周)施工进度计划是（ ）性计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","控制",false,{"key":16,"text":17,"correct":14},"B","支撑",{"key":19,"text":20,"correct":21},"C","实施",true,{"key":23,"text":24,"correct":14},"D","阶段","P249-250 月、旬(周)施工进度计划是实施性的作业计划。作业计划应分别在每月、旬(周)末，由项目部提出目标和作业项目，通过工地例会协调之后编制。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]