[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126090":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126090,792,1,"单选题","以下选项中属于合同风险分散和转移的措施是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","增设风险合同条款",false,{"key":16,"text":17,"correct":14},"B","加强索赔管理",{"key":19,"text":20,"correct":21},"C","向保险公司投保",true,{"key":23,"text":24,"correct":14},"D","增设保值条款","P216-217 本题对合同风险的管理与防范措施知识点的考查，需考生了解识记。 1.合同风险的规避：充分利用合同条款；增设保值条款；增设风险合同条款；增设有关支付条款；外汇风险的回避；减少承包方资金、设备的投入；加强索赔管理，进行合理索赔。 2.风险的分散和转移：向保险公司投保；向分包商转移部分风险。 3.确定和控制风险费 ：工程项目部必须加强成本控制，制定成本控制目标和保证措施。编制成本控制计划时，每一类费用及总成本计划都应适当留有余地。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]