[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126070":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1126070,792,1,"单选题","预应力张拉应由（）主持。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","操作班长",false,{"key":16,"text":17,"correct":14},"B","施工员",{"key":19,"text":20,"correct":14},"C","技术员",{"key":22,"text":23,"correct":24},"D","项目技术负责人",true,"P273-275 预应力张拉人员控制： (1)承担预应力施工的单位应具有相应的施工资质。 (2)预应力张拉施工应由工程项目技术负责人主持。 (3)张拉作业人员应经培训考核，合格后方可上岗。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]