[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126067":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126067,792,1,"单选题","项目进度控制总目标可按单位工程分解为（）分目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","交工",true,{"key":16,"text":17,"correct":18},"B","时间",false,{"key":20,"text":21,"correct":18},"C","阶段",{"key":23,"text":24,"correct":18},"D","专业","P249-250 本题对进度控制总目标及其分解知识点的考查，需考生了解识记。 (1)总目标对工程项目的施工进度加以控制，并以实现施工合同约定的竣工日期为最终目标，总目标应按需要进行分解。 (2)按单位工程分解为交工分目标，制定子单位工程或分部工程交工目标。 (3)按承包的专业或施工阶段分解为阶段分目标，重大市政公用工程可按专业工程分解进度目标分别进行控制；也可按施工阶段划分确定控制目标。 (4)按年、季、月分解为时间分目标，适用于有形象进度要求时。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]