[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126065":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126065,792,1,"单选题","市政公用工程施工组织设计应经（）批准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","监理工程师",{"key":19,"text":20,"correct":21},"C","总承包单位技术负责人",true,{"key":23,"text":24,"correct":14},"D","项目技术负责人","P225-231 施工组织设计的审批应符合下列规定: 1)施工组织设计可根据需要分阶段审批； 2)施工组织设计应经总承包单位技术负责人审批并加盖企业公章。 施工方案的审批应符合下列规定: 1)施工方案应由项目技术负责人审批。重点、难点分部(分项)工程的施工方案应由总承包单位技术负责人审批。 2)由专业承包单位施工的分部(分项)工程，施工方案应由专业承包单位的技术负责人审批，并由总承包单位项目技术负责人核准备案。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]