[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126064,792,1,"单选题","施工项目管理的核心是施工（ ）管理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量",false,{"key":16,"text":17,"correct":14},"B","安全",{"key":19,"text":20,"correct":21},"C","成本",true,{"key":23,"text":24,"correct":14},"D","工期","P218-219 施工项目管理的核心是施工成本管理，应根据企业下达的成本控制目标，管理控制各种支出。通过项目投标与合同签订、项目标价分离、下达项目部目标管理责任书、编制项目部实施计划、进行过程控制、成本计算和分析等一系列项目管理工作，实现工程项目的预期收益。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]