[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126052,792,1,"单选题","喷锚暗挖法二次衬砌应在（ ）后施工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初期支护变形稳定",true,{"key":16,"text":17,"correct":18},"B","地层变形稳定",false,{"key":20,"text":21,"correct":18},"C","隧道贯通",{"key":23,"text":24,"correct":18},"D","防水层施工完成","P314-316 现浇混凝土二次衬砌在隧道初期支护变形稳定后进行。初期支护临时支撑的拆除应严格按设计要求分段进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]