[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126036":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1126036,792,1,"单选题","进行不合格让步接收时，项目部应向（）提出书面让步接收申请。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质监站",false,{"key":16,"text":17,"correct":14},"B","监理",{"key":19,"text":20,"correct":21},"C","发包方",true,{"key":23,"text":24,"correct":14},"D","接管方","P255-257 进行不合格让步接收时,工程施工项目部应向发包方提出书面让步接收申请,记录不合格程度和返修的情况,双方签字确认让步接收协议和接收标准。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]