[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1126035":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1126035,792,1,"单选题","项目经理部应及时进行施工进度控制总结的时间节点为在施工（ ）后。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度计划完成",true,{"key":16,"text":17,"correct":18},"B","分项工程完成",false,{"key":20,"text":21,"correct":18},"C","分部工程完成",{"key":23,"text":24,"correct":18},"D","分部工程进度计划完成","P250-252 在工程施工进度计划完成后，项目部应编写施工进度控制总结，以便企业总结经验，提高管理水平。",{"id":6,"name":27,"category":28,"favorite":29},"二建市政工程实务","建筑工程",0]